George Massey Tunnel replacement could have been cheaper than expected

Delta staff report says the bridge could have been built for nearly $1 billion less than projected

A bridge to replace the aging George Massey Tunnel could be significantly cheaper than projected, according to a recently-released City of Delta report.

Since the previous report to council in October 2017, new cost projections have come to light. In October, the estimated cost for a replacement ranged from $3.5 billion for a replacement bridge to $5.8 million for maintaining the existing tunnel and building a new bridge in another area.

However, according to a Delta staff report dated Feb. 21, 2018, the lowest bid for bridge construction came in at $2.6 billion — nearly $1 billion lower than the expected cost.

“Unlike the Patullo project which is only part-way through the environmental assessment process, the tunnel replacement project is shovel-ready,” the report reads. “[It] has received its environmental assessment certificate and has completed the bidding process.”

The George Massey Tunnel replacement project has been on hiatus since the NDP government took over from the B.C. Liberals last year.

RELATED: B.C. pauses Massey bridge work to conduct new review

In September, 2017, Transportation Minister Claire Trevena announced an independent technical review of the project, saying previous reviews by the Liberal government may not have looked at all possibilities.

About $70 million had already been spent on the $3.5 billion new crossing, including funds allocated to the building of a new counterflow lane on the Alex Fraser Bridge to help relieve congestion in the area while the project’s plan is sorted. Work on the counterflow lane began in early December and is expected to be complete in the fall.

READ MORE: Work begins on Alex Fraser Bridge counterflow lane

The technical review of the Massey replacement project got underway with engineer Stan Codwell in November of last year. The review is intended to look at the lifespan, safety, seismic vulnerability and current congestion of the tunnel, as well as the technical information already produced for the replacement project.

Results from that review are expected in the coming months.

— with files from Ashley Wadhwani and James Smith



grace.kennedy@northdeltareporter.com

Like us on Facebook and follow us on Twitter

Just Posted

Langley cheerleaders climb their way to the Summit

A team from Langley Cheer & Athletics is on their way to Florida to compete in early May.

UPDATE: IHIT investigating suspicious death in South Surrey

Roads closed at 12 Avenue and 28 Avenue

Sound wall under construction at 216th Interchange

Work is picking up steam at the new interchange crossing site.

Throwback Thursday: April 26, 2018

Help us caption a photo from Langley’s past!

Cloverdale fourth grader wants to take learning to the next dimension

Riley Markowsky-Qadir wants his classmates to be able to learn in 3D

WATCH: Small fire at Langley spa manufacturer creates big plume

Black smoke from a Thursday evening fire at a spa maker could be seen for miles.

NAFTA talks hold Foreign Affairs Minister in Washington, substitute heads to NATO summit

NAFTA talks keeping Foreign Affairs Minister Chrystia Freeland, sends substitute to NATO summit

Britain gives long-lost Franklin expedition ships to Canada, Inuit

Deeds to HMS Erebus and HMS Terror signed over to Canada and Inuit Heritage Trust

Grief over deadly Toronto van attack sinks in

Three days after rampage, people still gathering at memorial to lay flowers and honour victims

Liberals urged to tax e-commerce services like Netflix

Trudeau has been adamant that his government wouldn’t increase taxes on online subscriptions

Why some B.C. daycares didn’t opt in to subsidy program

Deadline passes for program aimed at laying foundation for universal child care

WATCH: Moms Stop The Harm respond to opioid crisis

Someone asked her if she does the work for her son. McBain said: “No, actually. I do it for your son.”

Been a long day? Here’s cute puppies in training

Group is training next batch of assistance dogs at Vancouver International Airport

B.C. skydiver lands safely after cutting away main chute

Greater Victoria emergency services called after witnesses saw spiralling chute

Most Read