Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


Like us on Facebook and follow us on Twitter.

Just Posted

Metro gas prices hit 155.7 cents a litre and higher

Lower Mainland could see 1.60 cents by April

BREAKING: Patient airlifted from two-vehicle crash in Langley Wednesday morning

Fraser Highway at 232nd Street is closed in both directions. People are asked to find another route.

Proposed slaughterhouse in South Langley evokes considerable ire

Large delegation of Langley residents came out to oppose a poultry abattoir.

Cloverleaf Preschool must find new home after 26 years in Cloverdale community

Christ the Redeemer Church terminated tenancy, finding 86-year-old Bell Hall unsafe

LETTER: Lack of tree protection for Langley short-sighted but expected

One Langley letter writer calls Township council’s inaction on a tree protection bylaw disappointing.

Ottawa proposes restricted pot labels, packages

Packaging will include red stop sign with marijuana leaf and ‘THC’

B.C.-pioneered wood construction on a roll internationally

Washington state considers mandatory engineered wood for public buildings

Cops say gun-toting robbers used fake police lights to pull over victims

Information wanted on North Shuswap robbery, police impersonation, burnt vehicle, motorhome theft.

BCHL Today: Surrey Eagles and Powell River Kings close to advancing

BCHL Today is a (near) daily look at what’s going on around the league and the junior A world.

Plane filled with smoke lands at Nanaimo Airport

WestJet flight came in from Vancouver

VSO to perform ‘Star Wars’ music while 1977 movie plays on big screen

Three shows for the classic at iconic Orpheum Theatre this summer

B.C. emergency alert system being tested Wednesday

Alarm tone and message will play on TV and radio

BC Conservatives pumped by poll results

Surge in popularity has BC party picturing elected representatives in Victoria

5 to start your day

A serious crash in Langley, Surrey man wanted in connection to vicious assault and more

Most Read