Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Langley baseball team brings aid to Puerto Rico

Blaze raised $50,000 for the trip to

Fraser Valley Thunderbirds bound for playoffs

Minor midget team of mostly Langley players secures spot over Family Day weekend

Langley chamber joins call to kill ‘no pipeline ever’ law

Bill C-69 will hurt the local Langley economy, Chamber warns

World Day of Prayer returns to Langley

St. Joseph’s Catholic Church is hosting the annual day on March 1.

Young Langley family plagued by angry cab customers

A couple rents a house formerly used by a cab firm, and unwelcome visitors knocking.

VIDEO: North Delta elementary school closed following stabbing that left cop, woman in serious condition

An off-duty police officer and a woman were injured outside of the school Wednesday afternoon

70% of Canadians agree with mandatory vaccines for children: poll

The debate for pro and anti vaccinations has heated up after a measles outbreak in Vancouver

VIDEO: Woman, off-duty cop in serious condition after stabbing outside B.C. elementary school

The officer was interceding in an alleged assault when he and the woman were stabbed

5 to start your day

Two people are in critical condition after stabbing, searchers recover body of missing snowshoer and more

‘A little baloney’ in PM’s claim about solicitor-client privilege on SNC-Lavalin

The Conservatives and NDP want Trudeau to waive that privilege so Wilson-Raybould can offer her side of the story

Proposed edible pot rules are wasteful, would leave products tasteless: critics

When Canada legalized weed last fall, it only allowed fresh or dried bud, oil, plants and seeds

Most Read